Pembaruan utama
- East China R32 references stayed at ¥63,500–64,500 per tonne OilChem’s 25 November East China table kept R32 and refrigerant-grade R22 unchanged from the previous working day. A ¥65,500 factory figure on the same page is not in that table.
- Tianjin commissions data-centre waste-heat heating A 23 November notice says cooling-water heat from the national supercomputing centre now heats 160,000 m². The stated coal and CO₂ savings are the publisher’s estimate.
- New Zealand shows a pilot heat pump for 120°C steam The University of Waikato described the pilot on 25 November and showed it in Hamilton on 26 November. The “three or four times” remark is not a measured COP for this unit.
- EXQUISHEAT reviews 28 food and beverage processes At its 24–25 November meeting in Berlin, the project said temperature ranges from 11 companies broadly match the literature. Load profiles still decide whether a heat pump fits.
- HEATEXPO puts industrial heat, cooling and waste heat on one floor The Dortmund fair ran on 24–26 November, with about 275 exhibitors. Hall 7 covered large heat pumps, industrial waste heat and process heat. The fair is not a performance test.
- A refinery review sets an order for low-grade waste heat Hydrocarbon Processing on 24 November says to quantify streams and check direct recovery before ORC, heat pumps or absorption cooling. Feasibility studies are not operating results.
East China R32 references stayed at ¥63,500–64,500 per tonne
OilChem’s 25 November East China table kept R32 and refrigerant-grade R22 unchanged from the previous working day. A ¥65,500 factory figure on the same page is not in that table.
The 09:01 table lists refrigerant-grade R22 at ¥17,000 per tonne, R125 pada ¥52,000–53,000, R134a pada ¥63,500–65,000 dan R410A pada ¥55,000–56,000. Every row’s change from the previous working day is zero. The note says these are point ex-works references, not daily averages. Mysteel’s 14:23 reprint matches the R32 and refrigerant-grade R22 ranges.
The page is marked as AI-generated. Its outlook also refers to a factory offer near ¥65,500 per tonne for China-market and export supply together. That figure is outside the table. Mysteel’s reprint puts feedstock-grade R22 at ¥12,000 per tonne, while the morning table puts it at ¥13,000–14,000. Confirm grade, packaging and delivery terms before using either number in a budget.
Tianjin commissions data-centre waste-heat heating
A 23 November notice says cooling-water heat from the national supercomputing centre now heats 160,000 m². The stated coal and CO₂ savings are the publisher’s estimate.
The Tianjin Economic-Technological Development Area said the Tianhe Digital Industrial Park project is in operation. Tianjin TEDA Energy Technology and Broad Air Conditioning implemented it. A magnetic-bearing heat pump lifts heat from the supercomputing centre’s cooling water. A storage tank and an electromagnetic boiler sit with it. The heated area covers eight park buildings and the supercomputing centre’s office, 160,000 m².
The notice says the tank is charged on off-peak electricity and the boiler is the backup for extreme cold. It estimates about 600 tonnes of standard coal and about 1,560 tonnes of CO₂ a year. Those figures are labelled as a calculation, not a completed year of metered heat. The same notice does not give supply and return temperatures, heat-pump capacity or measured electricity use.
New Zealand shows a pilot heat pump for 120°C steam
The University of Waikato described the pilot on 25 November and showed it in Hamilton on 26 November. The “three or four times” remark is not a measured COP for this unit.
The Ahuora Energy Centre, with Excel Refrigeration and Air Conditioning, built what the university calls New Zealand’s first pilot-scale heat pump that can make steam. It is designed for 120°C steam dan 85°C hot water, for dairy, meat, food and wood processing that uses low-pressure steam. The Energy Efficiency and Conservation Authority co-funded the project and the 26 November showing at The Pā.
Project lead Keegan Hall’s “three or four times the heat” sentence describes heat pumps in general. The university does not publish a measured COP, steam flow or operating hours for this pilot. Director Tim Walmsley said the next step is a larger installation, starting with an early adopter. One example given is warm wastewater used to make steam for milk sterilisation and hot water for cleaning. That is an illustration, not a reported plant result.
EXQUISHEAT reviews 28 food and beverage processes
At its 24–25 November meeting in Berlin, the project said temperature ranges from 11 companies broadly match the literature. Load profiles still decide whether a heat pump fits.
GEA Heating & Refrigeration hosted the project’s second general assembly. EXQUISHEAT said it has analysed 28 processes from 11 companies in six European countries. The preliminary findings say the temperature ranges generally match published literature, and that load profiles matter when judging a heat-pump integration. Average process handbooks are described as coming soon. They were not on the project site at this review.
A first look at 20 stakeholder interviews lists four recurring barriers: investment return, limited knowledge of the technology, difficulty of tying a heat pump into an existing plant, and scarce finance. Standardised guidance for four food and beverage applications is still being written. The meeting did not publish site measurements or a selected machine.
HEATEXPO puts industrial heat, cooling and waste heat on one floor
The Dortmund fair ran on 24–26 November, with about 275 exhibitors. Hall 7 covered large heat pumps, industrial waste heat and process heat. The fair is not a performance test.
tab.de reported the opening on 24 November: about 275 exhibitors from 16 countries. New Hall 7 covers heat and cooling generation and industrial uses, including large heat pumps, combined heat and power, geothermal energy, plant engineering and industrial waste-heat use. The published agenda also includes waste heat from data centres and process-heat storage. VDMA Power Systems’ Dennis Rendschmidt said industrial process heat cannot be decarbonised by one technology, because temperatures and operating needs differ.
The German Heat Pump Association had announced a session for 25 November, 15:15–16:15, on the Blue Stage in Hall 4, about taking large heat pumps from concept to order. That announcement is dated 22 October. tab.de confirms the fair opened; it does not report measured performance from any machine on the floor. Opening hours announced by the association were 10:00–17:00 on 24 and 25 November, and 10:00–16:00 on 26 November.
A refinery review sets an order for low-grade waste heat
Hydrocarbon Processing on 24 November says to quantify streams and check direct recovery before ORC, heat pumps or absorption cooling. Feasibility studies are not operating results.
The review covers refineries, petrochemical plants, LNG and gas processing. Its order is: measure heat sources and sinks from plant data; use pinch analysis and the heat-exchanger network so recoverable heat is not turned into lower-value power while a heating need remains; look at steam and condensate recovery; then choose among ORC, heat pumps, vapour recompression, absorption cooling or desalination according to the site’s utility balance. The authors say ORC is the most widely demonstrated heat-to-power route for steady streams above about 70–90°C, and that this is not a rule for every plant.
The article separates field examples, feasibility studies, simulations and conceptual screens. It cites a Sinopec Guangzhou case in which steam-condensate heat drove a lithium-bromide refrigeration unit for process cooling. Reported paybacks and megawatt figures in the review stay inside the prices, running hours and capital costs of each source study. They are not this week’s operating results, and they do not transfer to another site.
Datang
Standards check on 29 November. China’s open standards portal still lists GB/T 18837-2026 and GB/T 27941-2026 as in force, with an implementation date of 1 November. The Ministry of Ecology and Environment list is still headed by the 16 October notice on the 2027 allocation plan. No newly issued standard was added. The EU climate-action F-gas documentation page still shows 11 November as the latest publication date for the listed implementing regulations. The Japan Standards Association’s November index does not itself name individual refrigeration or heat-pump standards. No new United Kingdom text was confirmed this week.
- 23 November: Tianjin announces that the data-centre waste-heat heating project is in operation. A draft for comment opens on part 4 of the refrigeration-system and heat-pump safety and environmental requirements, covering operation, maintenance, repair and recovery.
- 24–26 November: HEATEXPO runs in Dortmund. EXQUISHEAT meets in Berlin on 24–25 November. Hydrocarbon Processing publishes the low-grade waste-heat review on 24 November.
- 25–26 November: The University of Waikato describes the pilot steam heat pump and shows it in Hamilton. GEOFLEXheat’s webinar was on the 25 November agenda; no measured results were found afterwards. The German Heat Pump Association’s large-heat-pump session was listed for 25 November.
- 27 November: A second draft for comment opens, on technical requirements for renewing multi-split air-conditioning (heat pump) systems. The notice does not assign a published standard number.
- 1 Desember: Forum dan Penghargaan Pompa Panas EHPA, Brussels.
- 2 Desember, 15: 00 – 16: 30 CET: IEA HPT Project 68 webinar online tentang pompa panas suhu tinggi dalam pengeringan makanan.
- 7 – 11 Desember: Pertemuan Komite Eksekutif Multilateral Fund 99 dijadwalkan di Montreal.
Sumber
- OilChem morning note, 25 November, East China price table
- Mysteel, reprint of the 25 November East China quotations
- Tianjin Economic-Technological Development Area, 23 November
- University of Waikato, 25 November
- EXQUISHEAT, Berlin meeting note, 25 November
- tab.de, HEATEXPO opening, 24 November
- German Heat Pump Association, HEATEXPO session announcement
- Hydrocarbon Processing, low-grade waste-heat review, 24 November
- Hefei General Machinery & Electrical Products Inspection Institute, draft-for-comment list
- Draft for comment, part 4 on operation, maintenance, repair and recovery, 23 November
- Draft for comment, multi-split system renewal, 27 November
- SAMR, GB/T 18837-2026 status
- SAMR, GB / T 27941 -2026 status
- Kementerian Ekologi dan Lingkungan Hidup, ODS dan Pemberitahuan HFC
- European Commission, F-gas documentation
- Japanese Standards Association, November publication index
- EHPA, webinar GEOFLEXheat, 25 November
- EHPA, Forum dan Penghargaan Pompa Panas, 1 Desember
- IEA HPT Project 68, webinar pengering makanan, 2 Desember
- Multilateral Fund, India proposals paper, meeting dates in the week-47 source
本期要点
- 华东 R32 参考价仍为 6.35–6.45 万元/吨 隆众资讯 11 月 25 日的华东价格表中,R32 和制冷剂级 R22 较前一工作日未变。同页另写的 6.55 万元厂家报盘不在这张表里。
- 天津投运数据中心余热供暖 11 月 23 日的消息称,国家超算中心冷却水余热已为 16 万平方米供暖。所写节煤和二氧化碳减排是发布方测算。
- 新西兰展示面向 120°C 蒸汽的中试热泵 怀卡托大学 11 月 25 日介绍这台中试装置,26 日在汉密尔顿展示。所说的「一份电对应三到四份热」不是这台装置的实测 COP。
- EXQUISHEAT 整理 28 个食品饮料工艺 项目在 11 月 24–25 日的柏林会议上称,11 家企业的温度区间与文献大体一致。热泵是否合适,仍要看负荷曲线。
- HEATEXPO 把工业供热、供冷和余热放在同一展馆 多特蒙德展会于 11 月 24–26 日举行,约 275 家展商。7 号馆集中大型热泵、工业余热和过程热。展会不是性能测试。
- 一篇炼化综述给出低品位余热的筛选顺序 《Hydrocarbon Processing》11 月 24 日写道,应先量化物流并检查直接回收,再考虑 ORC、热泵或吸收式制冷。可行性研究不是运行结果。
华东 R32 参考价仍为 6.35–6.45 万元/吨
隆众资讯 11 月 25 日的华东价格表中,R32 和制冷剂级 R22 较前一工作日未变。同页另写的 6.55 万元厂家报盘不在这张表里。
09:01 的价格表列出制冷剂级 R22 1.7 万元/吨,R125 5.2–5.3 万元/吨,R134a 6.35–6.5 万元/吨,R410A 5.5–5.6 万元/吨。各行相对前一工作日的涨跌都是 0。页面说明这些是时点出厂参考价,不是日均价。我的钢铁网 14:23 的转载与 R32、制冷剂级 R22 的区间一致。
该页标注内容由 AI 生成。行情展望另写主流工厂对中国市场和出口的报盘约 6.55 万元/吨,这个数字不在价格表中。我的钢铁网转载把原料级 R22 写成 1.2 万元/吨,早报表则为 1.3–1.4 万元/吨。用于采购预算前,应核对品级、包装和交货条件。
天津投运数据中心余热供暖
11 月 23 日的消息称,国家超算中心冷却水余热已为 16 万平方米供暖。所写节煤和二氧化碳减排是发布方测算。
天津经济技术开发区称,天河数字产业园项目已投运。实施方是天津经开能源技术有限公司和远大低碳技术(天津)有限公司。磁悬浮热泵提升国家超算中心冷却水的热量,并与蓄热水箱、电磁锅炉一起运行。供热范围覆盖园区 8 栋楼和超算中心办公楼,面积 16 万平方米。
消息称蓄热水箱在谷电时段蓄热,电磁锅炉用于极寒天气备用。测算约为每年节约标准煤 600 吨、减排二氧化碳 1560 吨。这是测算,不是已完成的全年计量。同一则消息没有给出供回水温度、热泵容量或实测用电。
新西兰展示面向 120°C 蒸汽的中试热泵
怀卡托大学 11 月 25 日介绍这台中试装置,26 日在汉密尔顿展示。所说的「一份电对应三到四份热」不是这台装置的实测 COP。
Ahuora 能源中心与 Excel Refrigeration and Air Conditioning 合作,制成大学所称的新西兰第一台可产蒸汽的中试热泵。设计目标是 120°C 蒸汽和 85°C 热水,面向使用低压蒸汽的乳品、肉类、食品和木材加工。新西兰能效与节能署参与资助项目,以及 11 月 26 日在 The Pā 的展示。
项目负责人 Keegan Hall 所说的「一份电得到三到四份热」,讲的是热泵的一般情况。大学没有公布这台中试的实测 COP、蒸汽流量或运行小时。中心主任 Tim Walmsley 说,下一步是放大应用,并从首个工业用户开始。文中举的例子是用温热废水制取牛奶杀菌蒸汽和清洗热水。这是举例,不是已报告的工厂结果。
EXQUISHEAT 整理 28 个食品饮料工艺
项目在 11 月 24–25 日的柏林会议上称,11 家企业的温度区间与文献大体一致。热泵是否合适,仍要看负荷曲线。
GEA Heating & Refrigeration 主办了项目第二次全体会议。EXQUISHEAT 称已分析 6 个欧洲国家、11 家企业的 28 个工艺。初步结果是温度区间与已发表文献大体一致,判断热泵能否接入时负荷曲线很重要。平均工艺手册被写成即将公开。本次核对时,项目网站上还没有这些手册。
对最初 20 次利益相关方访谈的初步分析列出四类反复出现的障碍:投资回报、对技术了解有限、接入现有工厂的难度,以及资金不足。面向四类食品饮料用途的标准化说明仍在编写。这次会议没有公布现场测量或选定机型。
HEATEXPO 把工业供热、供冷和余热放在同一展馆
多特蒙德展会于 11 月 24–26 日举行,约 275 家展商。7 号馆集中大型热泵、工业余热和过程热。展会不是性能测试。
tab.de 于 11 月 24 日报道展会开幕:约 275 家展商,来自 16 个国家。新的 7 号馆集中供热与供冷设备及工业用途,包括大型热泵、热电联产、地热、成套装置和工业余热利用。已公布的议程还包括数据中心余热和过程热蓄热。VDMA Power Systems 的 Dennis Rendschmidt 说,工业过程热不能靠单一技术实现低碳替代,因为温度和运行需求并不相同。
德国热泵协会此前宣布,11 月 25 日 15:15–16:15 在 4 号馆 Blue Stage 讨论大型热泵如何从方案走到订单。该预告的日期是 10 月 22 日。tab.de 确认展会已经开幕,没有报告现场任何设备的实测性能。协会公布的开放时间是 11 月 24 日和 25 日 10:00–17:00,26 日 10:00–16:00。
一篇炼化综述给出低品位余热的筛选顺序
《Hydrocarbon Processing》11 月 24 日写道,应先量化物流并检查直接回收,再考虑 ORC、热泵或吸收式制冷。可行性研究不是运行结果。
这篇综述面向炼油、石化、液化天然气和天然气处理装置。顺序是:用工厂数据测量热源和热阱;做夹点和换热网络分析,避免附近仍有用热需求时把可回收热量拿去发电;再看蒸汽和凝结水回收;然后按现场公用工程平衡,在 ORC、热泵、蒸汽再压缩、吸收式制冷或海水淡化之间选择。作者写道,对大约 70–90°C 以上的稳定物流,ORC 是已示范较多的热转电路线,这不是每座工厂的规则。
文章把现场实例、可行性研究、模拟和概念筛选分开。它引用中国石化广州的一个例子:蒸汽凝结水的热量驱动溴化锂制冷,为工艺供冷。文中的回收期和兆瓦数字,只属于各来源研究自己的价格、运行小时和投资。它们不是本周的运行结果,也不能搬到另一个现场。
接下来哪天
11 月 29 日核对标准。国家标准全文公开系统仍将 GB/T 18837-2026 和 GB/T 27941-2026 标为现行,实施日期仍是 11 月 1 日。生态环境部目录最新一条仍是 10 月 16 日的 2027 年配额分配方案。没有新发布的标准写入本期。欧盟气候行动署 F-gas 文件页上,已列出的实施条例最近发布日仍是 11 月 11 日。日本规格协会 11 月发行目录页本身没有写出单项制冷或热泵标准名称。英国本周没有核到新的文本。
- 11 月 23 日 天津公布数据中心余热供暖项目已投运。合肥通用机电产品检测院就《制冷系统及热泵 安全与环境要求》第 4 部分征求意见,范围是运行、维护、检修和回收。
- 11 月 24–26 日 HEATEXPO 在多特蒙德举行。EXQUISHEAT 于 24–25 日在柏林开会。《Hydrocarbon Processing》于 24 日刊出低品位余热综述。
- 11 月 25–26 日 怀卡托大学介绍蒸汽热泵中试,并在汉密尔顿展示。GEOFLEXheat 研讨会列在 25 日议程上,其后没有见到实测结果。德国热泵协会的大型热泵专场列在 25 日。
- 11 月 27 日 第二份征求意见稿发布,主题是多联式空调(热泵)系统更新技术规范。公告没有给出已发布的标准号。
- 12 月 1 日 欧洲热泵论坛与颁奖活动,布鲁塞尔。
- 12 月 2 日 22:00–23:30(北京时间) IEA HPT Project 68 食品干燥高温热泵线上研讨会。
- 12 月 7–11 日 蒙特利尔议定书多边基金执行委员会第 99 次会议拟在蒙特利尔举行。
出处
- 隆众资讯早间提示,11 月 25 日,华东价格表
- 我的钢铁网,转载 11 月 25 日华东报价
- 天津经济技术开发区,11 月 23 日
- 怀卡托大学,11 月 25 日
- EXQUISHEAT,柏林会议说明,11 月 25 日
- tab.de,HEATEXPO 开幕报道,11 月 24 日
- 德国热泵协会,HEATEXPO 专场预告
- Hydrocarbon Processing,低品位余热综述,11 月 24 日
- 合肥通用机电产品检测院,征求意见列表
- 征求意见稿,运行、维护、检修和回收第 4 部分,11 月 23 日
- 征求意见稿,多联式系统更新,11 月 27 日
- 国家标准全文公开系统,GB/T 18837-2026 状态
- 国家标准全文公开系统,GB/T 27941-2026 状态
- 生态环境部,消耗臭氧层物质和氢氟碳化物通知目录
- 欧盟委员会,含氟气体文件页
- 日本规格协会,11 月发行目录
- 欧洲热泵协会,11 月 25 日 GEOFLEXheat 研讨会
- 欧洲热泵协会,12 月 1 日热泵论坛与颁奖
- IEA HPT Project 68,12 月 2 日食品干燥研讨会
- 多边基金印度项目建议书,其中写有第 99 次会议日期;该文件在第 47 周已引用