Your plant has ammonia refrigeration and a useful process-hot-water demand. Check whether heat availability, required temperatures and demand timing actually overlap. A similar industry or system name alone is not enough.现场有氨制冷系统和有效的工艺热水需求。先核对可用热量、所需温度与用热时段是否匹配;行业或系统名称相似还不够。
What cannot be carried over哪些不能直接套用
Hot-water volume and steam displacement are plant-reported; COP, investment and payback are not independently verified here. The piping, oil-management and hygiene arrangements require a separate review for your live ammonia system.热水量和蒸汽替代属于用户口述;本站没有独立核验的 COP、投资及回收期。管路、油管理与卫生隔离方案仍须结合本项目在运氨系统单独复核。
What to prepare我应准备什么
Record discharge and condensing conditions separately, recovery-loop temperatures and flow, hot-water supply/return and demand hours, compressor/auxiliary electricity and the displaced heat bill. Add dates, units and sources, and mark missing measurements.分别记录排气与冷凝工况、回收回路温度和流量、热水供回温度与需求时段、压缩机及辅机电耗、被替代热源账单。保留日期、单位、来源,并标出待补测量。
These links do not copy case values into your project. Keep unknowns and sources explicit. A preparation sheet is not a feasibility result; screening does not replace ammonia safety, engineering or procurement review.这些入口不把案例数值填入你的项目。未知项和来源应如实保留;准备单不等于项目可行,初筛不替代氨安全、工程或采购复核。