Food processing: ammonia HP recovers refrigeration reject heat to 80°C wash water

Anonymized slaughter-plant retrofit: ammonia mid-temp heat pump couples to existing ammonia refrigeration and displaces a gas boiler for wash/sanitation hot water.

Engineering data

Case type
Anonymized field reference
Data status
anonymized_field_reference
Industry
Food
Source temperature
28–32°C
Sink temperature
75–80°C
Temperature lift
≈ 43 K
Heating or cooling duty
380 kW
Architecture
Ammonia mid-temperature heat pump coupled via evaporative condenser interface
Result status
Gas boiler largely displaced for wash heat; refrigeration reject heat reused
Key risk
Ammonia safety; seasonal refrigeration load vs heat demand mismatch
Existing system
Natural-gas boiler for wash/sanitation heat; ammonia refrigeration reject heat dumped on evaporative condenser
Refrigerant
R717 (ammonia)
COP
3.5–4
Annual savings
Reported ~54% daily heat-energy cost cut vs gas boiler; ~¥0.45 M/y class savings in public summary
Estimated payback
Reported ~2.3 years (static)

Project background

An East China food-processing site used a gas boiler for daily wash and sanitation heat while ammonia screw packs rejected condenser heat outdoors. Energy cost and unused reject heat motivated a heat-pump retrofit.

Source / inputs

Source: ammonia plant condenser heat near 30°C. Sink: ~20/80°C hot water. Unit heating capacity ~380 kW class, COP ~3.8 in the published parameter table. Customer identity omitted.

Heat pump solution

An ammonia mid-temp heat pump evaporates against refrigeration reject heat and rejects to the process hot-water loop, replacing the gas boiler for wash/sanitation duty while remaining compatible with the existing ammonia plant.

COP & savings

Published table: heating ~380 kW, input ~100 kW, COP ~3.8, 20/80°C water. Operating summary reports large daily OPEX cut versus gas. Independent site audit not performed by this site.

Investment / ROI notes

Public summary cites CAPEX on the order of ¥1 M and static payback ~2.3 years from annual OPEX savings—tariffs and hours are site-specific.