湖州西塞:2 MW 空氣熱泵儲能報道滿負荷運行,蒸汽約 540°C

Lüchu Technology (9 Apr 2026): a 2 MW-class very-high-temperature heat-pump storage demo at Xisai Science Valley, Huzhou, Zhejiang, China, reached full load. It uses air as the heat-pump fluid and molten salt as storage, and is reported to release superheated steam near 540°C at a COP of 1.41 from about 45°C waste heat. Not a process-steam heat pump, and not independently metered here.

Run detailed calculation with this case

工程數據

案例類型
公開來源案例 — 數據來自公開報告、論文或廠商資料
數據狀態
公開來源案例
數據來源
Lüchu Technology note via China Energy Storage Network, 13 Apr 2026: https://www.escn.com.cn/news/show-2246741.html — Manufacturer retrospective, 29 Jan 2026: https://www.lvchutec.com/newsinfo/10980848.html
審閱 / 日期
Editorial (Open Thermal AI) · 2026-11-02
行業
工業製造
熱源溫度
45°C
熱匯溫度
540°C
溫升
≈ 495 K
供熱/製冷負荷
2000 kW
架構
空氣熱泵給熔鹽充熱,再釋放高溫蒸汽——熱泵儲能,不是閉式產汽再串機械蒸汽再壓縮
結果狀態
The builders reported full-load operation on 9 Apr 2026. Electric input is about 1.5 MW and heating output about 2 MW. COP 1.41 is source-reported for the 45°C source. A separate 8 MW / 400°C phase was announced earlier and is not treated here as this operating unit.
Key risk
The April 2026 full-load account and a manufacturer retrospective of a February 2025 test give different dates and COPs. Their equipment/configuration relationship is not established here. Neither a short test nor a heat-pump COP proves annual storage-cycle performance.
原有系統
電制熱儲能示範,可釋放工業蒸汽或支撐發電;報道沒有把它寫成某一條點名工藝線的改造
製冷劑
Air (R729) as the heat-pump fluid; molten salt as storage
COP
1.41
年度節能 / 減排
所用報道未給出經計量的年節能量
預計回收期
未披露

項目背景

湖州工業控制技術研究院與浙江綠儲科技報道,西塞科學谷的特高溫熱泵儲能示範達到滿負荷。案例庫把它放在儲熱出汽。它能產蒸汽,但設備是給熔鹽充熱的空氣熱泵。

敘述性輸入

熱源約 45°C。電功率約 1.5 MW,制熱約 2 MW。報道蒸汽約 540°C,熔鹽約 565°C,壓縮機出口 600°C 級,進口約 355°C。

熱泵方案

空氣是熱泵工質。熱量存在熔鹽裏,再以高溫蒸汽釋放。報道還提到棄風棄光消納和電廠靈活性。這些是儲能用途,不是單一工藝蒸汽改造。

COP 與節能

Full load was reported on 9 Apr 2026 with COP 1.41 at a 45°C source. The same note says COP can exceed 2 if the waste-heat temperature is higher. No independent test record is reproduced here.

投資回報要點

所用報道沒有投資與回收期。

FAQ

這是獨立計量覈驗案例嗎?

不是。證據等級爲公開來源。滿負荷和 COP 1.41 是項目建設方的報道。本站未對該機組計量。

更早的 8 MW 項目算在本條裏嗎?

No. An 8 MW / 400°C phase was a separate construction announcement aimed at later commissioning. This page records the 2 MW unit that was reported at full load in April 2026.

What changed in the 2 November 2026 review?

A manufacturer retrospective dated 29 January 2026 reports a 2 MW demonstration test in February 2025: 225 continuous full-power hours and COP 1.43. Keep this separate from the April 2026 account (COP 1.41) until unit identity and test boundaries are reconciled; do not treat 225 hours as annual operating hours.