← All cases

Public-source case — figures from published reports, papers, or vendor materials

South Korea · Ajin P&P Daegu: 108°C hot water for paper drying

LG reported the start of heat-pump operation in early July 2026. Project 68 separately describes the site's heat-pump and steam-recompression integration concept.

Run detailed calculation with this case

Engineering data

Case type
Public-source case — figures from published reports, papers, or vendor materials
Data status
Public-source case
Reviewer / date
Editorial (Open Thermal AI) · 2026-11-21
Industry
Pulp & paper
Source temperature
Not disclosed
Sink temperature
Not disclosed
Temperature lift
Not applicable
Heating or cooling duty
Not disclosed
Architecture
Electric heat pump with oil-free magnetic-bearing compression. The Project 68 concept adds mechanical vapour recompression (MVR) for steam supply.
Result status
The July 2026 supplier announcement reports operation of the hot-water heat-pump system.
Key risk
1,040 RT is maximum cooling capacity. The 118°C value is a unit limit. The Project 68 steam concept does not provide annual operating results for the integrated system.
Existing system
Paper drying uses a steam network.
Refrigerant
R1233zd(E) (LG heat-pump stage)
COP
Not disclosed
Annual energy / emissions savings
Not disclosed in the sources reviewed.
Estimated payback
Not disclosed in the sources reviewed.

Project background

The Daegu paper-mill installation is part of a South Korean industrial R&D programme.

Narrative inputs

Confirm recoverable exhaust heat at each paper grade, the hot-water temperatures, and steam demand and pressure at the header.

Heat pump solution

Use the heat-pump hot-water stage and the proposed steam stage as separate equipment boundaries when comparing bids.

COP & savings

The reviewed primary sources provide unit specifications and a process concept. Annual heat delivery, total electrical input and integrated COP remain unconfirmed.

Investment / ROI notes

A stand-alone heat-pump payback is not established here. Use your site's metered loads, utility prices, integration cost and backup duty for a separate estimate.