Italy · Cartiere di Guarcino: 741 kW low-pressure steam stage

Cannon Bono reports operation of its heat-pump stage on cogeneration cooling heat in October 2026. The downstream MVR is a separate stage.

Run detailed calculation with this case

Engineering data

Case type
Public-source case — figures from published reports, papers, or vendor materials
Data status
Public-source case
Reviewer / date
Editorial (Open Thermal AI) · 2026-11-21
Industry
Pulp & paper
Source temperature
Not disclosed
Sink temperature
Not disclosed
Temperature lift
Not applicable
Heating or cooling duty
741 kW
Architecture
PUSH2HEAT electric screw-compressor heat-pump demonstrator, with mechanical vapour recompression specified downstream in the design.
Result status
Cannon Bono reports 741 kW heating output and 1.2 t/h steam for the heat-pump stage.
Key risk
Supplier COP 5.25 belongs to the low-pressure heat-pump stage. The 6.5 bar figure is the design target after MVR, and annual integrated performance remains unconfirmed.
Existing system
The decorative-paper mill requires steam and is served by a cogeneration installation with recoverable cooling heat.
Refrigerant
R1233zd(E)
COP
Not disclosed
Annual energy / emissions savings
Not disclosed in the sources reviewed.
Estimated payback
Not disclosed in the sources reviewed.

Project background

The Italian mill hosts two distinct PUSH2HEAT demonstrations. This entry covers the Cannon Bono electric heat pump, separate from the site's absorption heat transformer.

Narrative inputs

The supplier quotes 115°C and 1.7 bar(a) at the heat-pump steam outlet. The design paper pairs 105°C with 1.7 bar at the first stage. Check steam state, pressure reference and measuring point before reuse.

Heat pump solution

Use cooling heat to make low-pressure steam. The design adds MVR to raise pressure for the mill network.

COP & savings

Cannon Bono reports 141 kW electrical input with 741 kW output at the heat-pump stage. Ask for matched downstream steam output, both stages' electricity and total operating hours before estimating annual impact.

Investment / ROI notes

A stand-alone heat-pump payback is not established here. Use your site's metered loads, utility prices, integration cost and backup duty for a separate estimate.