Australia · Hardwick Meatworks: 1 MW heat pump and oil heat recovery
The ARENA-funded final report separates heat-pump output, direct oil heat recovery and gas top-up across two production periods.
Run detailed calculation with this case一键代入详细计算
Engineering data
- Case type
- Public-source case — figures from published reports, papers, or vendor materials
- Data status
- Public-source case
- Data source
- ARENA knowledge bank, project final report: https://arena.gov.au/knowledge-bank/hardwick-meatworks-heat-pump-installation-and-power-upgrade-demonstration-final-report/ — Hardwick final report, logging periods and heat split: https://arena.gov.au/assets/2025/08/Hardwick-Meatworks-Heat-Pump-Installation-and-Power-Upgrade-Demonstration-Final-Report.pdf
- Reviewer / date
- Editorial (Open Thermal AI) · 2026-11-21
- Industry
- Food
- Source temperature
- Not disclosed
- Sink temperature
- Not disclosed
- Temperature lift
- Not applicable
- Heating or cooling duty
- 1000 kW
- Architecture
- Ammonia heat pump connected to the existing refrigeration system, direct oil heat recovery and hot-water storage.
- Result status
- For October 2023–September 2024, the final report assigns 45% of hot-water energy to the heat pump and 16% to oil heat recovery.
- Key risk
- The often quoted 61% combines both recovery routes. It refers to hot-water energy for the reported period. Gas still provides final top-up to 85°C.
- Existing system
- Gas water heaters supply final process water. The plant already uses ammonia refrigeration.
- Refrigerant
- R717
- COP
- Not disclosed
- Annual energy / emissions savings
- Not disclosed in the sources reviewed.
- Estimated payback
- Not disclosed in the sources reviewed.
Project background
The Kyneton, Victoria demonstration combined a heat pump with an electrical-supply upgrade. The public installation is the source reference for the separate on-site teaching example.
Narrative inputs
Report figures: 1 MW heat-pump rating. Combined logged thermal output was reported at 1,266 kW for October 2023–September 2024 and 1,088 kW for October 2024–May 2025.
Heat pump solution
Route recovered heat to hot-water storage and retain the gas heaters for the final rise to the process temperature.
COP & savings
The report gives 5,059 logged hours (5,512 annualised) for October 2023–September 2024 and 2,461 logged hours (4,277 annualised) for October 2024–May 2025. The latter period had lower production.
Investment / ROI notes
A stand-alone heat-pump payback is not established here. Use your site's metered loads, utility prices, integration cost and backup duty for a separate estimate.