Japan · Honda Yorii: 140°C steam field trial for paint-line drying
Mayekawa and Honda are testing a NEDO-supported steam heat pump on an automotive paint line, as reported in October 2026.
Run detailed calculation with this case一键代入详细计算
Engineering data
- Case type
- Public-source case — figures from published reports, papers, or vendor materials
- Data status
- Public-source case
- Data source
- Mayekawa, 15 Oct 2026, full release pp. 2–3: https://www.mayekawa.co.jp/ja/uploads/news/e98091b04219f04fd91fcd37d1310b9c.pdf — NEDO development brief: https://www.nedo.go.jp/content/800019306.pdf
- Reviewer / date
- Editorial (Open Thermal AI) · 2026-11-21
- Industry
- Manufacturing
- Source temperature
- Not disclosed
- Sink temperature
- 140°C
- Temperature lift
- Not applicable
- Heating or cooling duty
- Not disclosed
- Architecture
- Mayekawa screw-compressor heat pump with a flash tank for steam generation from heated water.
- Result status
- Mayekawa reports field testing and preliminary findings on steam-supply function and load response by July 2026.
- Key risk
- COP 3 is a development-system result from Mayekawa's Moriya tests. Honda's field-trial COP, annual savings and commercial acceptance are unconfirmed.
- Existing system
- Fossil-fuel boiler steam is the comparison baseline.
- Refrigerant
- R1336mzz(Z)
- COP
- Not disclosed
- Annual energy / emissions savings
- Not disclosed in the sources reviewed.
- Estimated payback
- Not disclosed in the sources reviewed.
Project background
Mayekawa identified Honda's Saitama Yorii finished-vehicle plant as the field-trial site in its 15 October 2026 release.
Narrative inputs
The tested use is 140°C steam. The development-unit specification gives 0.36 MPa absolute at that temperature. The factory's load profile and steam flow are undisclosed.
Heat pump solution
The project checks steam generation, response to variable demand and controls on an actual production line.
COP & savings
The supplier's bench-test COP should remain tied to the development unit. April 2027 is the supplier's target for starting sales.
Investment / ROI notes
A stand-alone heat-pump payback is not established here. Use your site's metered loads, utility prices, integration cost and backup duty for a separate estimate.