Netherlands · Kervo: 800 kW for fruit-processing hot water and steam
Danfoss's November 2026 case describes a Servex installation using cold-storage refrigeration heat for process hot water and steam generation.
Run detailed calculation with this case一键代入详细计算
Engineering data
- Case type
- Public-source case — figures from published reports, papers, or vendor materials
- Data status
- Public-source case
- Data source
- Danfoss, 4 Nov 2026: https://www.danfoss.com/en/service-and-support/case-stories/dcs/industrial-heat-pump-turns-recovered-heat-into-process-heat/ — EHPA case summary, citing Danfoss: https://ehpa.org/heat-pump-stories/industrial-electrification-is-bearing-fruit/
- Reviewer / date
- Editorial (Open Thermal AI) · 2026-11-21
- Industry
- Food
- Source temperature
- Not disclosed
- Sink temperature
- Not disclosed
- Temperature lift
- Not applicable
- Heating or cooling duty
- 800 kW
- Architecture
- Servex integrates a transcritical CO₂ refrigeration circuit with separate hydrocarbon heat-pump stages.
- Result status
- Danfoss reports 800 kW of heating capacity for the combined arrangement.
- Key risk
- The 800 kW is reported heating capacity for the arrangement. Steam-only duty, source and sink temperatures, whole-system COP and annual savings are undisclosed.
- Existing system
- Cold storage needs refrigeration, and fruit processing needs hot water and steam.
- Refrigerant
- R744 / R600a / R600 (separate circuits)
- COP
- Not disclosed
- Annual energy / emissions savings
- Not disclosed in the sources reviewed.
- Estimated payback
- Not disclosed in the sources reviewed.
Project background
Danfoss published the operating application at Dutch fruit processor Kervo on 4 November 2026. EHPA also describes the installation and links to the supplier account.
Narrative inputs
For a comparable project, obtain hourly cooling duty, hot-water temperatures and steam pressures. Check refrigerant charge and local requirements for hydrocarbon circuits.
Heat pump solution
Separate useful heat from the hot-water and steam stages and meter both against the incremental electricity used.
COP & savings
The sources describe the application and nameplate scale. They give no metering period or verified annual performance.
Investment / ROI notes
A stand-alone heat-pump payback is not established here. Use your site's metered loads, utility prices, integration cost and backup duty for a separate estimate.