Vicinity Kendall, Cambridge: 35 MW river-source heat pump for district steam, installation targeted by 2028

Vicinity Energy (4 Nov 2025): construction has started on a 35 MW river-source heat pump at the Kendall plant in Cambridge, Massachusetts, to make district steam from the Charles River. Everllence (formerly MAN Energy Solutions) supplies the heat pump. Installation is targeted by 2028. This is under construction, and it is district steam rather than a factory process line.

Engineering data

Case type
Public-source case
Data status
public_source
Industry
District heating
Source temperature
Not disclosed
Sink temperature
Not disclosed
Temperature lift
Not applicable
Heating or cooling duty
35000 kW
Architecture
River-source industrial heat pump for a district steam network; Everllence heat pump, DCO Energy installation
Result status
Construction agreements were announced on 4 Nov 2025. Demolition of a gas boiler was described as underway. Heat-pump installation is targeted by 2028. No operating performance exists.
Key risk
35 MW is a planned nameplate, not a measured steam output. River-source district steam is not the same duty as factory process steam at 150–180°C.
Existing system
Existing Kendall district-steam plant; a natural-gas boiler is being removed to make room for the heat pump
Refrigerant
Not stated in the construction note used here
COP
Not disclosed
Annual savings
Not stated as a measured total; the plant is not operating
Estimated payback
Not disclosed

Project background

Vicinity Energy, DCO Energy, and Everllence announced an industrial heat-pump complex for the Kendall Square district-energy plant in Cambridge, Massachusetts. The library files it under district heating and under construction. It is steam, but the customer is a city steam network.

Narrative inputs

Planned capacity: 35 MW thermal from river water to district steam. Temperatures, refrigerant, COP, and hours are not in the 4 Nov 2025 note.

Heat pump solution

A river-water heat pump will sit at the existing Kendall plant and use the site's electrical interconnection. One gas boiler is removed. The company's name for the product is eSteam. Installation work is assigned to DCO; the heat pump supplier is Everllence.

COP & savings

There is no operating COP. The only scale figure is the announced 35 MW. A separate company remark about progress elsewhere is not copied here as performance of Kendall.

Investment / ROI notes

No investment or payback is in the construction note used here.