Frozen-food cold storage. The verification report records one package with a specified cooling capacity of 189 kW.为冻品冷库供冷。核证报告记录了一台规格制冷量为 189 kW 的机组。
結果の状態结果状态
The JCM registry records operation from December 2014. JQA verified the project’s emissions calculation for February–July 2015.JCM 登记资料记载项目于 2014 年 12 月投运。JQA 核证了 2015 年 2 至 7 月的项目减排计算。
PipeChina reports that its Haimen gas station in Nantong started operating an expander-generator in November 2025.国家管网集团披露,江苏南通海门站的天然气膨胀发电机组于 2025 年 11 月投运。
For the separate blast-cell design, Lineage reported 20% better energy efficiency per pound and 50% faster freezing versus its previous standard cells.对单独试用的新型速冻间,Lineage 披露其单位重量能效较原标准速冻间提高 20%,速冻速度提高 50%。
The DOE case attributes 170 billion Btu per year of energy savings to the 1998 steam-system control revisions.美国能源部将每年 1,700 亿 Btu 的节能量归于 1998 年的全厂蒸汽系统控制调整。
JCM records operation starting in April 2017. The registered project covers both chilled water and compressed air.JCM 登记资料记载项目于 2017 年 4 月投运,登记项目同时覆盖冷冻水与压缩空气。
EECA records commissioning in March 2022. A project case study reports post-installation monitoring, including extra electricity use and reduced coal use.
LG reported the start of heat-pump operation in early July 2026. Project 68 separately describes the site's heat-pump and steam-recompression integration concept.
The CO₂ figure is an operator disclosure through the supplier. The €6.75 million order covers the wider package. Heat-pump duty, COP and stand-alone payback are undisclosed.
Belgian sugar-refining installation: the November 2025 IEA HPT card records commissioning operation and subsequent compressor operation at full capacity. Annual benefits remain estimates.
温度上昇
≈ 63 K
建築
GEAスクリューコンプレッサー付きクローズドnペンタンヒートポンプ。蒸気から蒸気への熱回収。
結果の状態
The November 2025 IEA HPT card reports part-load commissioning followed by full compressor capacity after modifications; heating COP still awaited validation.
Design COP is about 2 at a very large temperature lift; the guaranteed COP itself is not published in the press note. CO₂ totals differ between the two sources.
公開報告書、論文、またはベンダー資料――出典および仮定表示
運用記録および技術的詳細运行记录与技术资料
Public sources (Turboden, 17 Feb 2026; IEA HPT demo card): a large heat pump plus mechanical vapor recompression at a delfort specialty-paper mill, reported at 12 MWth and about 20 t/h of superheated steam. Not independently metered here.
Turboden announced full operation on 17 Feb 2026 and said startup COP was about 10% above the guaranteed value. The IEA card records about 2,000 test hours from July to October 2025. Vendor wording calls it the largest steam-producing heat pump built; this site does not audit that ranking.
Public sources (SPH and the NEFI AHEAD demo card): at Takeda's Vienna pharmaceutical site, a butane heat pump and a Spilling steam compressor are reported to deliver about 2.5 t/h at 11 bar(a) / 184°C. Commissioning is given as September 2025. Not independently metered here.
The plant opened in September 2025. AIT confirmed monitoring had started in November 2025. Project 68’s October 2026 webinar summary describes the cascade and 184°C steam. Completed 4,000-hour results and seasonal system COP remain unpublished in the sources reviewed.
Skyven reported sustained COP 8.0 at its 1 MWth Texas steam-heat-pump demonstration center on 2 September 2026, up from 6.5 at commissioning. This is a supplier disclosure; the announcement does not give the demo temperature pair or measurement boundary.
建築
アークトゥルスの水性蒸気ヒートポンプ。メーカーは真空フラッシュの後、多段式蒸気圧縮を説明
結果の状態
The September 2026 announcement replaces the earlier roadmap with a supplier-reported result of 8.0. The numeric COP field remains blank because comparable test conditions are missing.
Dongfang Electric (3 Feb 2026 start-up): Dongfang Electric reports an 890 kW steam heat pump and booster at the Taiji Fuling pharmaceutical plant in Chongqing, China, lifting about 40°C waste heat to 165°C saturated steam at a stated COP of 2.7. Not independently metered here.
温度上昇
≈ 125 K
建築
高温蒸気ヒートポンプとブースター圧縮機。電気入力は890kWの暖房用に約330kWの電力供給を報告
結果の状態
Dongfang Electric’s own 3 February 2026 announcement confirms commissioning at Taiji Fuling and reports about 330 kW electrical input, 890 kW rated heat and measured COP 2.7. This is a supplier report, not this site’s independent audit.
The 2026 submission gives about 700 kWth, whereas the earlier card gives 800 kW. Heating design COP 1.8 and combined heating/cooling COP 2.5 have different boundaries and are not a range. Annual hours and measured COP remain unknown.
公開報告書、論文、またはベンダー資料――出典および仮定表示
運用記録および技術的詳細运行记录与技术资料
The project team’s 2026 EHPA award submission reports successful commissioning and on-site steam production at Stella Polaris, Finnsnes: about 700 kWth, waste heat at 18–21°C and steam at 145°C. Public project disclosure, not independent field verification.
SPH / JOA demo card (installation year 2025): at Philip Morris Manufacturing & Technology Bologna, a two-stage heat pump turns dryer exhaust heat into saturated steam at 139°C and 2.5 bar(g). Rated duty is 650 kW. A FAT COP of 2.5 is source-reported, not remeasured here.
温度上昇
≈ 40 K
建築
Two-stage reciprocating heat pump (SPH) integrated by JOA with direct recovery from humid dryer exhaust
The April 2026 full-load account and a manufacturer retrospective of a February 2025 test give different dates and COPs. Their equipment/configuration relationship is not established here. Neither a short test nor a heat-pump COP proves annual storage-cycle performance.
公開報告書、論文、またはベンダー資料――出典および仮定表示
運用記録および技術的詳細运行记录与技术资料
Lüchu Technology (9 Apr 2026): a 2 MW-class very-high-temperature heat-pump storage demo at Xisai Science Valley, Huzhou, Zhejiang, China, reached full load. It uses air as the heat-pump fluid and molten salt as storage, and is reported to release superheated steam near 540°C at a COP of 1.41 from about 45°C waste heat. Not a process-steam heat pump, and not independently metered here.
The builders reported full-load operation on 9 Apr 2026. Electric input is about 1.5 MW and heating output about 2 MW. COP 1.41 is source-reported for the 45°C source. A separate 8 MW / 400°C phase was announced earlier and is not treated here as this operating unit.
Shanghai Electric (acceptance 9 May 2025): a 1.1 MW / 10.8 MWh molten-salt store coupled to a high-temperature heat pump, supplying industrial steam at a factory in Fengxian, Shanghai. This is thermal storage plus a heat pump, not a process-steam heat pump of the closed-cycle plus MVR type. Not independently metered here.
建築
単一タンク溶融サルト貯蔵装置を高温ヒートポンプに結合してグリーン蒸気用に
結果の状態
Shanghai Electric reported that after more than two months of trial operation the system passed the owner's acceptance on 9 May 2025 and entered commercial operation. Steam conditions are not published as one fixed pair.
Under construction. Capacity, up to 500,000 tonnes/year of steam and up to 100,000 tonnes/year of avoided CO₂ are project targets. The team quotes a design COP of up to 3.4. Operating COP and annual outcomes are unconfirmed.
公開報告書、論文、またはベンダー資料――出典および仮定表示
運用記録および技術的詳細运行记录与技术资料
Public project note: BASF has started construction at Ludwigshafen, Germany, of an open heat-pump system (GKT CompriVAP, formerly GIG Karasek) meant to turn steam-cracker waste heat into up to 50 MW of process steam. Commissioning is scheduled for mid-2027. This entry is under construction, not an operating case.
GKT reported on 3 September 2026 that the first compressors had been positioned and the evaporator stage, vessels, pumps and heat exchangers installed. Piping and electrical work continued. BASF’s commissioning target remains mid-2027.
Vicinity’s May 2026 update keeps its 35 MW Charles River heat-pump complex at Kendall on a 2028 installation target. The stated role is to preheat water for an electric boiler supplying district steam. It remains an engineering/construction project, not an operating heat-pump case.
建築
River-source heat recovery to preheat water for the district-steam electric boiler, per the May 2026 owner account
結果の状態
The 11 May 2026 owner update says heat-pump engineering is active and installation is planned by 2028. Kendall’s electric boiler entered service in November 2024; its eSteam supply is not evidence that the heat pump is operating.
Author field survey (2024-05): same ammonia HP architecture as plant A at a second Central China meat site; plant-reported ~200–300 m³/day hot water and ~¥100k/month steam savings, plus liquid-path and cleanliness lessons.