巴斯夫路德維希港:CompriVAP 開式熱泵,最多約 50 MW 工藝蒸汽,尚未投運

Public project note: BASF has started construction at Ludwigshafen, Germany, of an open heat-pump system (GKT CompriVAP, formerly GIG Karasek) meant to turn steam-cracker waste heat into up to 50 MW of process steam. Commissioning is scheduled for mid-2027. This entry is under construction, not an operating case.

Run detailed calculation with this case

工程數據

案例類型
公開來源案例 — 數據來自公開報告、論文或廠商資料
數據狀態
公開來源案例
審閱 / 日期
Editorial (Open Thermal AI) · 2026-11-21
行業
化工
熱源溫度
未披露
熱匯溫度
未披露
溫升
不適用
供熱/製冷負荷
50000 kW
架構
開式 CompriVAP 熱泵——與 delfort 紙廠的閉式熱泵串聯機械蒸汽再壓縮不是同一條路線
結果狀態
GKT reported on 3 September 2026 that the first compressors had been positioned and the evaporator stage, vessels, pumps and heat exchangers installed. Piping and electrical work continued. BASF’s commissioning target remains mid-2027.
Key risk
Under construction. Capacity, up to 500,000 tonnes/year of steam and up to 100,000 tonnes/year of avoided CO₂ are project targets. The team quotes a design COP of up to 3.4. Operating COP and annual outcomes are unconfirmed.
原有系統
路德維希港蒸汽裂解裝置的餘熱計劃用於工藝蒸汽;熱泵投運前仍由化石蒸汽承擔
製冷劑
Open heat-pump / vapor-compression arrangement under the CompriVAP name; fluid not restated here beyond the vendor's open-cycle description
COP
未披露
年度節能 / 減排
Source claim, for a plant that is not yet operating: about 100,000 t/a of emissions avoided
預計回收期
未披露

項目背景

巴斯夫在路德維希港爲 GKT(原 GIG Karasek)供貨的大型工業熱泵舉行了開工,系統名爲 CompriVAP。2026 年的一項創新獎說明重複了同一項目。機組尚未運行,因此案例庫同時標爲在建和工藝蒸汽。

敘述性輸入

項目團隊 2026 年獎項申報列 76°C 裂解工藝水、5.8 bar(a) 蒸汽、最多 60 噸/小時、約 47 MW。巴斯夫公開材料的規模表述爲約 50 MW,兩者均爲計劃裝置口徑。

熱泵方案

計劃用開式熱泵(CompriVAP)把裂解餘熱提升爲工藝蒸汽。GKT 負責設計、供貨和實施。這不是 delfort 公開的閉式異丁烷熱泵加機械蒸汽再壓縮。

COP 與節能

BASF reported the evaporator delivery in April. GKT’s September construction update said remaining compressor units were scheduled for November delivery. The sources reviewed do not confirm that delivery or commissioning.

投資回報要點

Investment and payback are not in the note used here. Any savings figure applies only after the mid-2027 commissioning target.

FAQ

這是獨立計量覈驗案例嗎?

不是。證據等級爲公開來源,而且工廠仍在建設。還沒有可以覈驗的運行測量。

爲什麼收錄尚未投運的項目?

規模大到如果省略,就會漏掉化工領域已公佈的主要蒸汽熱泵項目。在建標籤和正文把它排除在已投運集合之外。

Check your own steam project

Record the required steam pressure and load, the available heat-source temperature and duty, and when both are available.

BASF’s published capacity and benefits are targets for a project under construction. Use your own site data and verify the steam process and equipment suitability separately.

Review the steam data checklist

Open detailed analysis with my own data