BASF Ludwigshafen: CompriVAP open heat pump, up to 50 MW of process steam, not yet operating
Public project note: BASF has started construction at Ludwigshafen, Germany, of an open heat-pump system (GKT CompriVAP, formerly GIG Karasek) meant to turn steam-cracker waste heat into up to 50 MW of process steam. Commissioning is scheduled for mid-2027. This entry is under construction, not an operating case.
Run detailed calculation with this case一键代入详细计算
Engineering data
- Case type
- Public-source case — figures from published reports, papers, or vendor materials
- Data status
- Public-source case
- Data source
- GKT / Green Tech Valley note: https://www.greentech.at/en/basf-relies-on-styrian-innovation-for-a-major-project-in-ludwigshafen/ — BASF, 8 Apr 2026: https://www.basf.com/global/en/media/news-releases/2026/04/p-26-068 — GKT installation update, 3 Sep 2026: https://gkt-solutions.com/newsroom/news/basf-large-scale-heat-pump-installation-progress/ — BASF/GKT 2026 project submission hosted by EHPA: https://ehpa.org/heatpumpforum/awards-projects/open-loop-high-temperature-heat-pump-at-basf-in-ludwigshafen/
- Reviewer / date
- Editorial (Open Thermal AI) · 2026-11-21
- Industry
- Chemical
- Source temperature
- Not disclosed
- Sink temperature
- Not disclosed
- Temperature lift
- Not applicable
- Heating or cooling duty
- 50000 kW
- Architecture
- Open CompriVAP heat pump — a different route from the closed heat pump plus MVR used at the delfort paper mill
- Result status
- GKT reported on 3 September 2026 that the first compressors had been positioned and the evaporator stage, vessels, pumps and heat exchangers installed. Piping and electrical work continued. BASF’s commissioning target remains mid-2027.
- Key risk
- Under construction. Capacity, up to 500,000 tonnes/year of steam and up to 100,000 tonnes/year of avoided CO₂ are project targets. The team quotes a design COP of up to 3.4. Operating COP and annual outcomes are unconfirmed.
- Existing system
- Steam cracker at Ludwigshafen with waste heat that is planned to feed process steam; fossil steam remains until the heat pump is commissioned
- Refrigerant
- Open heat-pump / vapor-compression arrangement under the CompriVAP name; fluid not restated here beyond the vendor's open-cycle description
- COP
- Not disclosed
- Annual energy / emissions savings
- Source claim, for a plant that is not yet operating: about 100,000 t/a of emissions avoided
- Estimated payback
- Not disclosed
Project background
BASF marked the start of construction at Ludwigshafen for a large industrial heat pump supplied by GKT (formerly GIG Karasek) using the CompriVAP system. A 2026 innovation-award note repeats the same project. Because the unit is not operating, the library tags it as under construction as well as process steam.
Narrative inputs
The team’s 2026 award submission specifies 76°C cracker water and steam at 5.8 bar(a), up to 60 t/h, about 47 MW. BASF’s public materials describe the scale as around 50 MW. Both describe the planned plant.
Heat pump solution
An open heat pump (CompriVAP) is planned to upgrade cracker waste heat into process steam. GKT is the EPC for planning, supply, and implementation. This is not the closed isobutane heat pump plus MVR architecture published for delfort.
COP & savings
BASF reported the evaporator delivery in April. GKT’s September construction update said remaining compressor units were scheduled for November delivery. The sources reviewed do not confirm that delivery or commissioning.
Investment / ROI notes
Investment and payback are not in the note used here. Any savings figure applies only after the mid-2027 commissioning target.
FAQ
Is this a verified measured project?
No. Evidence level is public-source, and the plant is under construction. There is no operating measurement to verify.
Why list a project that is not operating?
The capacity is large enough that leaving it out would hide the main announced steam-heat-pump project in chemicals. The under-construction tag and the page text keep it out of the operating set.