← All cases

Public-source case — figures from published reports, papers, or vendor materials

BASF Ludwigshafen: CompriVAP open heat pump, up to 50 MW of process steam, not yet operating

Public project note: BASF has started construction at Ludwigshafen, Germany, of an open heat-pump system (GKT CompriVAP, formerly GIG Karasek) meant to turn steam-cracker waste heat into up to 50 MW of process steam. Commissioning is scheduled for mid-2027. This entry is under construction, not an operating case.

Run detailed calculation with this case

Engineering data

Case type
Public-source case — figures from published reports, papers, or vendor materials
Data status
Public-source case
Reviewer / date
Editorial (Open Thermal AI) · 2026-11-21
Industry
Chemical
Source temperature
Not disclosed
Sink temperature
Not disclosed
Temperature lift
Not applicable
Heating or cooling duty
50000 kW
Architecture
Open CompriVAP heat pump — a different route from the closed heat pump plus MVR used at the delfort paper mill
Result status
GKT reported on 3 September 2026 that the first compressors had been positioned and the evaporator stage, vessels, pumps and heat exchangers installed. Piping and electrical work continued. BASF’s commissioning target remains mid-2027.
Key risk
Under construction. Capacity, up to 500,000 tonnes/year of steam and up to 100,000 tonnes/year of avoided CO₂ are project targets. The team quotes a design COP of up to 3.4. Operating COP and annual outcomes are unconfirmed.
Existing system
Steam cracker at Ludwigshafen with waste heat that is planned to feed process steam; fossil steam remains until the heat pump is commissioned
Refrigerant
Open heat-pump / vapor-compression arrangement under the CompriVAP name; fluid not restated here beyond the vendor's open-cycle description
COP
Not disclosed
Annual energy / emissions savings
Source claim, for a plant that is not yet operating: about 100,000 t/a of emissions avoided
Estimated payback
Not disclosed

Project background

BASF marked the start of construction at Ludwigshafen for a large industrial heat pump supplied by GKT (formerly GIG Karasek) using the CompriVAP system. A 2026 innovation-award note repeats the same project. Because the unit is not operating, the library tags it as under construction as well as process steam.

Narrative inputs

The team’s 2026 award submission specifies 76°C cracker water and steam at 5.8 bar(a), up to 60 t/h, about 47 MW. BASF’s public materials describe the scale as around 50 MW. Both describe the planned plant.

Heat pump solution

An open heat pump (CompriVAP) is planned to upgrade cracker waste heat into process steam. GKT is the EPC for planning, supply, and implementation. This is not the closed isobutane heat pump plus MVR architecture published for delfort.

COP & savings

BASF reported the evaporator delivery in April. GKT’s September construction update said remaining compressor units were scheduled for November delivery. The sources reviewed do not confirm that delivery or commissioning.

Investment / ROI notes

Investment and payback are not in the note used here. Any savings figure applies only after the mid-2027 commissioning target.

FAQ

Is this a verified measured project?

No. Evidence level is public-source, and the plant is under construction. There is no operating measurement to verify.

Why list a project that is not operating?

The capacity is large enough that leaving it out would hide the main announced steam-heat-pump project in chemicals. The under-construction tag and the page text keep it out of the operating set.

Check your own steam project

Record the required steam pressure and load, the available heat-source temperature and duty, and when both are available.

BASF’s published capacity and benefits are targets for a project under construction. Use your own site data and verify the steam process and equipment suitability separately.

Review the steam data checklist

Open detailed analysis with my own data