Field preparation

Hot-water demand and waste-heat preparation

Choose one device or process and record each item. Leave unknowns blank; guidance and sources continue below.

Enable JavaScript for electronic entry. The blank checklist below can still be printed using your browser; the guide remains available.

Print blank sheet

Open Thermal AI · Blank sheet

Hot-water demand and waste-heat preparation

Sheet ID: ________________ · Template version: 2026-10-18.1

Site / workshop
 
Equipment tag / process
 
Recorded by
 
Survey date
 

This sheet collects evidence. Recorded does not mean verified or feasible; unknown values stay blank.

Recorded does not mean verified. Completion does not establish safety, feasibility or savings; professional review is still needed.

HW-01 · Identify the hot-water user · ________
Equipment tag, process/cleaning/domestic purpose.
Where to look; what to do if missing: Use process or cleaning procedures; do not assume hygiene requirements.
An equipment tag is the identifier on its label or drawing. If unavailable, record the name and location and mark the tag as unconfirmed; do not invent an official identifier.
Water-use purpose 
Process/cleaning procedure ID 
Record status□ Not reviewed □ Recorded □ Needs measurement □ Needs confirmation □ Not applicable (explain)
Evidence type 
Document ID / source reference 
Measurement point / object location 
Time or recording period 
Operating condition (production/cleaning/idle) 
Notes / related sheet ID 
Action owner 
Target date 
Reason not applicable 
Reviewer, date and comments (human review) 
HW-02 · Confirm the process requirement · ________
Required temperature, tolerance, batch/continuous operation and reviewer.
Where to look; what to do if missing: Use approved process documents; mark unconfirmed requirements for review.
Required process temperature (°C) 
Allowed variation (°C) 
Batch or continuous operation 
Process reviewer 
Record status□ Not reviewed □ Recorded □ Needs measurement □ Needs confirmation □ Not applicable (explain)
Evidence type 
Document ID / source reference 
Measurement point / object location 
Time or recording period 
Operating condition (production/cleaning/idle) 
Notes / related sheet ID 
Action owner 
Target date 
Reason not applicable 
Reviewer, date and comments (human review) 
HW-03 · Record actual inlet and supply temperatures · ________
Cold inlet and hot supply temperatures, points and times.
Where to look; what to do if missing: Use existing instruments or trends; distinguish actual readings from setpoints.
Actual inlet temperature (°C) 
Actual supply temperature (°C) 
Record status□ Not reviewed □ Recorded □ Needs measurement □ Needs confirmation □ Not applicable (explain)
Evidence type 
Document ID / source reference 
Measurement point / object location 
Time or recording period 
Operating condition (production/cleaning/idle) 
Notes / related sheet ID 
Action owner 
Target date 
Reason not applicable 
Reviewer, date and comments (human review) 
HW-04 · Check actual water consumption · ________
Flow or volume per batch, duration and frequency.
Where to look; what to do if missing: Use meters and production logs; circulation flow is not necessarily new hot-water demand.
Actual volume or flow and unit 
Duration and frequency 
Water meter ID 
Record status□ Not reviewed □ Recorded □ Needs measurement □ Needs confirmation □ Not applicable (explain)
Evidence type 
Document ID / source reference 
Measurement point / object location 
Time or recording period 
Operating condition (production/cleaning/idle) 
Notes / related sheet ID 
Action owner 
Target date 
Reason not applicable 
Reviewer, date and comments (human review) 
HW-05 · Record existing heat supply · ________
Steam, electricity or other heat; same-period energy, scope and tariff.
Where to look; what to do if missing: Use submeters and bills; mark unallocated use as unknown.
Current heating method 
Same-period energy and unit 
Tariff and metering scope 
Record status□ Not reviewed □ Recorded □ Needs measurement □ Needs confirmation □ Not applicable (explain)
Evidence type 
Document ID / source reference 
Measurement point / object location 
Time or recording period 
Operating condition (production/cleaning/idle) 
Notes / related sheet ID 
Action owner 
Target date 
Reason not applicable 
Reviewer, date and comments (human review) 
HW-06 · Record a candidate waste-heat stream · ________
Fluid, temperature, flow and units, existing use.
Where to look; what to do if missing: Use diagrams and trends; keep separate heat streams separate.
Waste-heat fluid and current use 
Source temperature (°C) 
Actual flow and unit 
Record status□ Not reviewed □ Recorded □ Needs measurement □ Needs confirmation □ Not applicable (explain)
Evidence type 
Document ID / source reference 
Measurement point / object location 
Time or recording period 
Operating condition (production/cleaning/idle) 
Notes / related sheet ID 
Action owner 
Target date 
Reason not applicable 
Reviewer, date and comments (human review) 
HW-07 · Align source and water-use times · ________
Same-date operating intervals and seasonal changes.
Where to look; what to do if missing: Compare simultaneous trends and shift logs; schedule collection if they are missing.
Overlap hours are the times when source heat is available and the process needs heat simultaneously. Compare both operating logs. Do not assume 8,760 hours or use only one side’s running hours. Storage for mismatched timing needs separate assessment.
Source dates and hours 
Demand dates and hours 
Seasonal changes 
Record status□ Not reviewed □ Recorded □ Needs measurement □ Needs confirmation □ Not applicable (explain)
Evidence type 
Document ID / source reference 
Measurement point / object location 
Time or recording period 
Operating condition (production/cleaning/idle) 
Notes / related sheet ID 
Action owner 
Target date 
Reason not applicable 
Reviewer, date and comments (human review) 
HW-08 · Check fluid separation and layout · ________
Isolation requirements, reviewer, distance, existing tanks and space.
Where to look; what to do if missing: Use process documents and a site sketch; do not assume source fluid can contact cleaning water.
Separation requirements and reviewer 
Distance and space 
Existing storage tanks 
Record status□ Not reviewed □ Recorded □ Needs measurement □ Needs confirmation □ Not applicable (explain)
Evidence type 
Document ID / source reference 
Measurement point / object location 
Time or recording period 
Operating condition (production/cleaning/idle) 
Notes / related sheet ID 
Action owner 
Target date 
Reason not applicable 
Reviewer, date and comments (human review) 

Guide source: https://www.openthermalai.com/en/insights/hot-water-waste-heat-match.html

Stored in this browser without automatic upload. Export a backup before clearing browser data or changing devices; cloud sync and full offline use are not provided.

Recorded does not mean verified. Completion does not establish safety, feasibility or savings; professional review is still needed.

Temperature, heat duty, timing and separation must be checked together. Start with a measurement plan, not a promised saving.

Four checks before a project

Having both waste heat and a hot-water demand does not establish a workable project. Check usable temperature, available heat duty, simultaneous demand and the separation required between fluids. If one is unknown, identify the measurement before selecting equipment.

Put both sides on one time axis

Record source and hot-water temperatures, flow with units, production shifts, cleaning and downtime over representative operation. Heat available at night cannot automatically serve daytime demand. Storage would require a separate assessment of capacity, losses, hygiene, space and cost.

A potential recovery stream may already serve another process. Do not allocate the same heat to two uses.

Understand the route

Where source conditions can meet the required temperature through a suitable heat exchanger, examine direct recovery. Where temperature upgrading is needed, assess a heat pump against the same useful demand. Include effects on the original refrigeration system, pumps, backup supply and integration. Useful recovered heat is not the same as net savings.

Use a blank checklist

Use the site measurement checklist, then compare the recovery routes and their boundaries. The anonymized food-plant reference illustrates an arrangement; plant-reported economics are not independently metered savings or a guarantee for your site.

Sources and limits

This is an editorial learning guide, not a plant audit or a measured savings result. Site inputs remain unknown until supplied and checked. Detailed design, procurement, hygienic and pressure-equipment decisions require qualified review. Read our editorial principles.