Çimko cement plant, Türkiye土耳其 Çimko 水泥厂
The supplier reports an air-cooled ORC using clinker cooler heat, in operation since June 2019. The disclosed 6.4 MWe is design peak capacity.供应商披露,项目于 2019 年 6 月投运,利用熟料冷却余热驱动空冷 ORC。6.4 MWe 为设计峰值。
Is a heat source or pressure reduction point worth measuring for power generation?现场有余热或一道减压工序,值得取数评估发电吗?
Start here if you have a usable heat stream such as hot water, thermal oil or exhaust gas. In an ORC, recovered heat vaporizes a working fluid. Expansion drives a generator, and a condenser rejects heat before the fluid recirculates.现场有热水、导热油或烟气等可利用的热流时,可先看这条路线。ORC 利用回收的热量蒸发工质,经膨胀带动发电机。工质在冷凝器放热后循环使用。
U.S. Department of Energy: waste heat to power美国能源部:余热发电技术说明
Where a process already reduces steam or gas pressure, an expander may recover part of the available work. For steam that still supplies a downstream process, compare a backpressure turbine or a screw expander with the existing pressure-reducing valve. Check whether the outlet steam can still meet the process heat demand.蒸汽或气体已有减压工序时,可评估用膨胀机回收部分可用功。蒸汽减压后仍需供给下游工艺时,可将背压汽轮机或螺杆膨胀机与现有减压阀比较,核对排汽能否继续满足工艺用热。
The supplier reports an air-cooled ORC using clinker cooler heat, in operation since June 2019. The disclosed 6.4 MWe is design peak capacity.供应商披露,项目于 2019 年 6 月投运,利用熟料冷却余热驱动空冷 ORC。6.4 MWe 为设计峰值。
A U.S. DOE case describes how the plant changed the controls for its existing backpressure turbine generator to follow steam demand.美国能源部案例记录该厂如何调整既有背压汽轮发电系统的控制,使其跟随用汽需求。
Check whether the heat or pressure difference is available for long enough without compromising existing production. Compare direct heat use where relevant before allocating the same heat to generation. Evaluate net power after auxiliaries and check operating hours and existing energy costs before estimating annual benefits.先确认余热或压差能否稳定利用,并满足原有生产要求。若同一股热可直接供工艺使用,先把直接利用纳入比较。估算全年效益前,核对扣除辅机后的净发电量、运行时段和现有能源费用。
Use the expander calculator for component performance. Net plant output and economics require a system review.可用膨胀机计算器试算设备性能。全厂净发电量和经济性需结合系统复核。